Overview


As owner and operator of the Fos Tonkin LNG terminal (liquefied natural gas), the company Elengy decided to extend operations on this site by proceeding to upgrading works and construction of new structures. Before the implementation of a new wharf, a new mooring system was implemented on the existing structure, with dynamic stress measurement and control in order to prevent the structure from being damaged by too important stresses.

Assignment


o Wind conditions definition
o Modeling of the behavior of 3 LNG tankers during mooring operations
o Selection of the new mooring system and implementation masterplan
o Design of the temporary mooring system for the works phase
o Drafting of tender documentation for the suppliers and participation in negotiations

Owner

Elengy

Key figures

Period of services

January 2010 - December 2011