SMA1 and BLV2 weirs are located on the Arve river, in the Haute-Savoie department. Each weir is composed of:
– A water intake equipped with screens to protect fishes and facilitate waste removal
– A riprap-protected paved inlet tunnel
– 2 VLH (Very Low Head) turbines that do not interrupt fish migrations or movements
– A fishway and a notch for raft or kayak use
– A production plant nearby
– An unloading platform with an assembly area
– A storage area, used during the construction and operation process
– A permanent footpath to access the weir (maintenance / operation)
– A 20 kV transmission line to transfer the energy to the nearest electrical substation
– a removable weir, with weir valves
– A concrete abutment (reinforced concrete)