AeroportInternationaldePortGentil-Infrastructurescotepisteetcoteville

Port Gentil international Airport – Airside and Landside infrastructures

Missions

Our services included three phases  :

  • Design Services and Contractors selection,
  • Construction Supervision,
  • ORAT (Operational Readiness and Airport Transfer).

The Gabonese government designated TOTAL Gabon as the Project Owner for the modernization and restructuring works of the International Airport of Port-Gentil and its upgrading to the standards of ICAO. The project includes namely:

  • Construction of a new Passenger Terminal Building (9,000 sqm),
  • Construction of a new Presidential Pavilion (1,000 sqm)
  • Extension and rehabilitation of runway, taxiways and apron,
  • Construction of roads and associated utilities on landside.

The Infrastructure Project constited in:

  • Two code E apron stands,
  • Two runway turn-pads,
  • A new code E taxiway and the refurbishment up to standards of existing taxiways,
  • Compliance works for the apron fuel pits,
  • Helicopter apron (11 positions),
  • GSE Road,
  • Airfield Ground Lighting compliance works,
  • Boundary fence including a vehicle access point with security screening,
  • Access roads and car parks (60,000 sqm),
  • External utility networks (water supply, sewage disposal, cable networks for power transmission and telecom data transmission…) and drainage system.

 

During the first phase, setec provided various services and assist the Project Owner for :

  • Project Preliminary and Detailed design and its financial estimates, for the various batches (Structural, MEP, Infrastructure…),
  • Construction Phasing,
  • Tender Documents (Drawings, Specifications, BoQ…),
  • Tender Process Management (from the identification of the interested parties to the recommendations to the Client for the awards.).

During the second phase, setec provided:

  • Project management : Technical, Administrative, Contractual and Financial,
  • Review and comment on shop drawings, samples and material certifications submitted by the Contractors, with Electronic Document Management System,
  • Monitoring the execution of the Contractor’s design,
  • General construction quality control,
  • Coordination of construction works between the various Contractors (project schedules…),
  • Assistance to the Client to resolve field questions and support construction,
  • Assistance to the Client to ensure certification of the Works at completion.

Challenges

Design Services, Contractors selection and Construction Supervision and Design Services during Construction

Key figures

Total amount oh the project:

16 000 000 €