An electricity operator was in the process of buying a group of 19 hydropower plants, located in the Alps and with a total capacity of 70 MW, and tasked setec with handling the due-diligence process prior to acquisition.
This included:
– Assessing existing infrastructures and equipment
– Conducting a regulatory and environmental assessment
– Re-evaluating hydrological processes
– Reviewing existing operational practices (energy simulation)