The Mathay Dam is a gravity dam built in 1912 for hydroelectric power generation purposes. The dam was later raised by installing 13 new valves (4 m high and 180 m wide).
Following an underwater inspection carried out by the Client in July 2018, major scouring at the downstream toe along the entire length of the dam were discovered, which called into question its stability. setec was tasked with managing the urgent and critical reinforcement project.