Le projet
Nos missions
Assisted by Cyrus industries, setec énergie et environnement conducted the following tasks:
- Technical due-diligence. Evaluation of potential solutions to be implemented
- Selection of an adequate solution, providing the client with all the necessary details
- Procurement process: tender documentation and evaluation
- Construction supervision and monitoring
- Acceptance of the works
Maître d’ouvrage
SYCTOM
Périodicité
July 2017 - July 2020
Challenges
We simplified the fire protection network, working towards respecting the APSAD R1 European norm. By doing so, we improved the reliability and efficiency of the firewater network.